| Peer-Reviewed

Obstacles to the Implementation of Joint-funded Road Projects in Cameroon

Received: 25 October 2021    Accepted: 22 November 2021    Published: 23 March 2022
Views:       Downloads:
Abstract

The main objective of this research is to analyse and evaluate the determinants of the failure of the effective and efficient implementation of jointly financed road infrastructure projects in Cameroon. Specifically, we first analyse and assess the institutional and administrative determinants of the failure to implement jointly financed road infrastructure projects in Cameroon effectively and efficiently. Secondly, we analyses and assess the techno-financial determinants of the failure to implement jointly financed road infrastructure projects in Cameroon effectively and efficiently. In both cases, our methodology opted for a hypothetic deductive method through a questionnaire developed from direct and semi-direct interviews with the implementers of jointly financed road projects. Our main results, which are consistent with our hypotheses, show that in both cases, administrative red tape, long contracting times, late payment of accounts, deficiencies in design offices, release of rights of way, and late signing of compensation decrees, negatively influence the effective and efficient execution of jointly financed road infrastructure projects in Cameroon. On the basis of these results, this study concludes that there is inefficiency and ineffectiveness in the execution of the said road projects. Thus, we make a series of recommendations to the public authorities in order to formulate new development programmed and policies to be implemented within the framework of the various strategies and levers necessary to promote better management of road works in Cameroon, through proposals for better managerial and technical management in order to address the various bottlenecks preventing the normal progress of jointly financed road infrastructure projects in Cameroon. We will also suggest some strategies that would allow the fluidity of procedures related to the implementation of jointly financed road infrastructure projects in Cameroon.

Published in American Journal of Engineering and Technology Management (Volume 7, Issue 1)
DOI 10.11648/j.ajetm.20220701.12
Page(s) 8-20
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2024. Published by Science Publishing Group

Keywords

Joint Financing, Achievements, Road Projects

References
[1] J. Audet, Amboise, “The research project in administration. A general guide to its preparation”, 1996.
[2] S. Arrowsmith, “National and international perspectives on the regulation of public directives: the current law and the case of reform” vol. 7 n ° 3, p. 65-82, 1998.
[3] F. G. Clifford, E. W. Larson, “Project management” published in July 2014.
[4] K. G. Cooper, “The rework cycle; benchmarks for project manager”, Project Management Journal, vol. 24; ° 1, p. 17-21, 1993.
[5] J. C. Corbel, “Project management: Fundamentals, methods“, tools published in July 2012.
[6] G. Corriveau, "To excel in project management", ed. Transcontinental and Fondation de l'Entrepreneurship, 2007.
[7] CAMERCAP-PARC / MINEPAT: How to improve the maturation of projects in Cameroon - published in April 2017.
[8] B. Cova, “International project marketing: a panorama of concepts and techniques”, Revue française du marketing, N ° 127/128, 1990.
[9] R. P. Declerck, M. A. Crener, “The strategic management of projects”, Men and techniques editions, 1980.
[10] R. J. Defillipi, M. B. Arthur, “Paradox in projet-basedenterprise: the case of film making”, California management review, vol. 40, n ° 299. p. 125-139, 1998.
[11] D. C. Torres, V. Foster, “Cameroon Infrastructure Report: A Continental perspective”, 2011.
[12] J. Frame Davison “The new Project Management with Ms Project” Microsoft Quebec press, 433 pages 2011.
[13] Gauthier. “The structure of the evidence. Social research "2nd edition, Quebec, University of Quebec press, p 132, 1993.
[14] V. Giard, Project management, Economica Paris June 1999, 171 pages.
[15] P. Jagou, “Concurrent Engineering: controlling costs, deadlines and quality” Editions HERMES,, 142 pages; Paris June 1993.
[16] D. B. Zoutene, "Exploratory study of the skills of project managers within consulting engineering firms: Case of a Quebec firm", p, June 42, 2013.
[17] S. Fernie, S. D. Green, S. J. Weller, R. Nwcombe, “Knowledge sharing: context, confusion and controversy” International Journal of Public Budgeting Accounting and Financial Management 12.2, p. 231-247, 2015.
[18] H. Marchat, “project management” Published in 275 pages; July 2008.
[19] J. Makessi "The impact of raw material supply difficulties on the product quality of SMEs in the agro-industrial sector in Gabon", p. 1-137? 1992.
[20] P. Mbenda, E. R. Bekono; "Deviance as a bad practice: Case of the public procurement system in Cameroon", International management; 163; P 153-164, 176; and 180, 2012.
[21] J. R. Meredith, S. J. Mantel “Project Management: A Managerial Approach”, ed. John Wiley and sons, 1985.
[22] Nortumbria; “Association of research in construction management “, 2-4, September 2002.
[23] A. Tchokogué. A. Nollet J, D. E Taleb, "Supply management in developing countries: context and challenges" Management International, 9. 4, p. 47-63, 2005.
[24] W. O’Shaugnessy, “Methodological guide to project development and management”, volume 1, SMG ed. 2011.
[25] M. E. Obiedjou “Due process and the procurement methods in the construction industry Eyimba.” 10-14 P 223-239, August 2005.
[26] P. Gaddis, “in Harvard Buissness Review“ the project manager in 1959.
[27] P. Bernoux, “the sociology of organizations“, IBN, February 2000.
[28] PMI “A guide to the Project Management Body of Knowledge”, Project Management Institute, Upper Dardy, 1996.
[29] Project Management Institute (PMI) “Guide to the body of knowledge in project management”, ed. ANSI / PMI, 2004.
[30] R. Rothery, “China’s legal framework for public procurement”, Journal of public procurement, 3. 3, p. 401-411, May 1999.
[31] D. P. Slevin, J. K. Pinto,“Project implementation profile: new toll for project managers”, project manager journal, vol. 17, n ° 3 P. 57-30, 1986.
[32] R. Takim, A. Akintoy,“Performance indicators for successfull construction project performance” Dans, Greenwood, D. éd, 18th conference, P. 545-555. University of Quebec Press, University Press, 1991.
[33] K. V. Thai, “Public procurement Re-examined”, Journal of Public Procurement 1. 1, p. 9-50.
Cite This Article
  • APA Style

    Thomas D’Aquin Biyindi, Reine Amaleke Kinogo, Fabrice Kwefeu Mbakop, Atemengue Onambelé. (2022). Obstacles to the Implementation of Joint-funded Road Projects in Cameroon. American Journal of Engineering and Technology Management, 7(1), 8-20. https://doi.org/10.11648/j.ajetm.20220701.12

    Copy | Download

    ACS Style

    Thomas D’Aquin Biyindi; Reine Amaleke Kinogo; Fabrice Kwefeu Mbakop; Atemengue Onambelé. Obstacles to the Implementation of Joint-funded Road Projects in Cameroon. Am. J. Eng. Technol. Manag. 2022, 7(1), 8-20. doi: 10.11648/j.ajetm.20220701.12

    Copy | Download

    AMA Style

    Thomas D’Aquin Biyindi, Reine Amaleke Kinogo, Fabrice Kwefeu Mbakop, Atemengue Onambelé. Obstacles to the Implementation of Joint-funded Road Projects in Cameroon. Am J Eng Technol Manag. 2022;7(1):8-20. doi: 10.11648/j.ajetm.20220701.12

    Copy | Download

  • @article{10.11648/j.ajetm.20220701.12,
      author = {Thomas D’Aquin Biyindi and Reine Amaleke Kinogo and Fabrice Kwefeu Mbakop and Atemengue Onambelé},
      title = {Obstacles to the Implementation of Joint-funded Road Projects in Cameroon},
      journal = {American Journal of Engineering and Technology Management},
      volume = {7},
      number = {1},
      pages = {8-20},
      doi = {10.11648/j.ajetm.20220701.12},
      url = {https://doi.org/10.11648/j.ajetm.20220701.12},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.ajetm.20220701.12},
      abstract = {The main objective of this research is to analyse and evaluate the determinants of the failure of the effective and efficient implementation of jointly financed road infrastructure projects in Cameroon. Specifically, we first analyse and assess the institutional and administrative determinants of the failure to implement jointly financed road infrastructure projects in Cameroon effectively and efficiently. Secondly, we analyses and assess the techno-financial determinants of the failure to implement jointly financed road infrastructure projects in Cameroon effectively and efficiently. In both cases, our methodology opted for a hypothetic deductive method through a questionnaire developed from direct and semi-direct interviews with the implementers of jointly financed road projects. Our main results, which are consistent with our hypotheses, show that in both cases, administrative red tape, long contracting times, late payment of accounts, deficiencies in design offices, release of rights of way, and late signing of compensation decrees, negatively influence the effective and efficient execution of jointly financed road infrastructure projects in Cameroon. On the basis of these results, this study concludes that there is inefficiency and ineffectiveness in the execution of the said road projects. Thus, we make a series of recommendations to the public authorities in order to formulate new development programmed and policies to be implemented within the framework of the various strategies and levers necessary to promote better management of road works in Cameroon, through proposals for better managerial and technical management in order to address the various bottlenecks preventing the normal progress of jointly financed road infrastructure projects in Cameroon. We will also suggest some strategies that would allow the fluidity of procedures related to the implementation of jointly financed road infrastructure projects in Cameroon.},
     year = {2022}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Obstacles to the Implementation of Joint-funded Road Projects in Cameroon
    AU  - Thomas D’Aquin Biyindi
    AU  - Reine Amaleke Kinogo
    AU  - Fabrice Kwefeu Mbakop
    AU  - Atemengue Onambelé
    Y1  - 2022/03/23
    PY  - 2022
    N1  - https://doi.org/10.11648/j.ajetm.20220701.12
    DO  - 10.11648/j.ajetm.20220701.12
    T2  - American Journal of Engineering and Technology Management
    JF  - American Journal of Engineering and Technology Management
    JO  - American Journal of Engineering and Technology Management
    SP  - 8
    EP  - 20
    PB  - Science Publishing Group
    SN  - 2575-1441
    UR  - https://doi.org/10.11648/j.ajetm.20220701.12
    AB  - The main objective of this research is to analyse and evaluate the determinants of the failure of the effective and efficient implementation of jointly financed road infrastructure projects in Cameroon. Specifically, we first analyse and assess the institutional and administrative determinants of the failure to implement jointly financed road infrastructure projects in Cameroon effectively and efficiently. Secondly, we analyses and assess the techno-financial determinants of the failure to implement jointly financed road infrastructure projects in Cameroon effectively and efficiently. In both cases, our methodology opted for a hypothetic deductive method through a questionnaire developed from direct and semi-direct interviews with the implementers of jointly financed road projects. Our main results, which are consistent with our hypotheses, show that in both cases, administrative red tape, long contracting times, late payment of accounts, deficiencies in design offices, release of rights of way, and late signing of compensation decrees, negatively influence the effective and efficient execution of jointly financed road infrastructure projects in Cameroon. On the basis of these results, this study concludes that there is inefficiency and ineffectiveness in the execution of the said road projects. Thus, we make a series of recommendations to the public authorities in order to formulate new development programmed and policies to be implemented within the framework of the various strategies and levers necessary to promote better management of road works in Cameroon, through proposals for better managerial and technical management in order to address the various bottlenecks preventing the normal progress of jointly financed road infrastructure projects in Cameroon. We will also suggest some strategies that would allow the fluidity of procedures related to the implementation of jointly financed road infrastructure projects in Cameroon.
    VL  - 7
    IS  - 1
    ER  - 

    Copy | Download

Author Information
  • Civil Engineering Laboratory, Higher Institute of Science, Arts and Grafts, Yaoundé, Cameroon

  • Civil Engineering Laboratory, Higher Institute of Science, Arts and Grafts, Yaoundé, Cameroon

  • Department of Renewable Energy, National Advanced School of Engineering, University of Maroua (UMa), Maroua, Cameroon

  • Civil Engineering Laboratory, Higher Institute of Science, Arts and Grafts, Yaoundé, Cameroon

  • Sections